1480.501 General.

All acquisitions made in accordance with this part, including simplified or commercial item acquisitions, must conform to all applicable requirements of the FAR and DIAR.

1480.502 [Reserved]

1480.503 Procedures for acquisitions under the Buy Indian Act.

(a) Commercial items or simplified acquisitions under this section must conform to the competition and price reasonableness documentation requirements of FAR 12.209 for commercial item acquisitions and FAR 13.106 for simplified acquisitions.

(b) When acquiring construction services, solicit proposals and evaluate potential contractors in accordance with FAR part 36 and DIAR subpart 1436.2.

(c) When acquiring A&E services, solicit proposals and evaluate potential contractors in accordance with FAR part 36 and DIAR subpart 1436.6.

(d) This paragraph (d) applies to solicitations that are not restricted to participation of IEEs.

(1) If an interested IEE is identified after a solicitation has been issued, but before the date established for receipt of offers, the contracting office must provide a copy of the solicitation to this enterprise. In this case, the CO:

(i) Will not give preference under the Buy Indian Act to the IEE; and

(ii) May extend the date for receipt of offers when practical.

(2) If more than one IEE is identified subsequent to the solicitation, but prior to the date established for receipt of offers, the CO may cancel the solicitation and re-compete it as an IEE set-aside.

(e) This paragraph (e) lists the clauses and provisions that must be inserted.

(1) Insert the clause at 1452.280-1, Notice of Indian Small Business Economic Enterprise set-aside, in accordance with 1480.401(c).

(2) Insert the clause at 1452.280-2, Notice of Indian Economic Enterprise set-aside, in accordance with 1480.401(d).

(3) Insert the clause at 1452.280-3, Indian Economic Enterprise subcontracting limitations, in accordance with 1480.601(b).

(4) Insert the clause at 1452.280-4, Indian Economic Enterprise representation, in accordance with 1480.801(a).

1480.504 Other circumstances for use of other than full and open competition.

(a) Other circumstances may exist where the use of an IEE set-aside in accordance with 1480.401(a) and FAR 6.302-5 is not feasible. In such situations, the requirements of FAR subparts 6.3 and 13.5 and DIAR subpart 1406.3 apply in justifying the use of the appropriate authority for other than full and open competition.

(b) Except as provided in FAR 5.202, all proposed acquisition actions must first be publicized in accordance with the requirements of FAR 5.2 and DIAR 1405.2.

(c) Justifications for use of other than full and open competition in accordance with this section must be approved in accordance with DIAR part 1406. These approvals are required for a proposed contract or for an out of scope modification to an existing contract.

1480.505 Debarment and suspension.

A misrepresentation by an offeror of its status as an IEE, failure to notify the CO of any change in IEE status that would make the contractor ineligible as an IEE, or any violation of the regulations in this part by an offeror or an awardee may be cause for debarment or suspension in accordance with FAR 9.406 and 9.407 and DIAR 1409.406 and 1409.407. IA must refer recommendations for debarment or suspension to the Director, Office of Acquisition and Property Management, Department of the Interior, in accordance with DIAR 1409.406 and 1409.407, through the Head of the Contracting Activity.