5837.170-2 Approval Requirements
(a) Acquisition of services through a contract or task order that is not performance based.
(1) For acquisitions at or below $50 million, obtain the review and approval of the CoCO.
(2) For acquisitions over $50 million up to $100 million, obtain the review and approval of the HCO.
(3) For acquisitions exceeding $100 million, obtain the review and approval of the Senior Procurement Executive (SPE).
(S-90) For each acquisition that is non-performance based, the contracting officer shall prepare a D&F for approval in accordance with paragraph DARS 5837.170-2(a). The D&F must be approved prior to release of the solicitation.
(S-91) The review and approval thresholds are based upon the total estimated cost of the acquisition.
(S-92) Technical and requirements personnel are responsible for providing accurate and complete data to the contracting officer to support their recommendation for other than a performance based acquisition.