Skip to main content
DFARS

DFARS

Change Number: DFARS Change 11/15/2024
Effective Date: 11/15/2024

217.7401 Definitions.

217.7401 Definitions.

As used in this subpart—

“Contract action” means an action which results in a contract.

(1) It includes contract modifications for additional supplies or services.

(2) It includes task orders and delivery orders.

(3) It does not include change orders, administrative changes, funding modifications, or any other contract modifications that are within the scope and under the terms of the contract, e.g., engineering change proposals, value engineering change proposals, and over and above work requests as described in subpart 217.77. For policy relating to definitization of change orders, see 243.204-70 .

“Definitization” means the agreement on, or determination of, contract terms, specifications, and price, which converts the undefinitized contract action to a definitive contract.

“Qualifying proposal” means a proposal that contains sufficient information to enable DoD to conduct meaningful analyses and audits of the information contained in the proposal.

“Undefinitized contract action” means any contract action for which the contract terms, specifications, or price are not agreed upon before performance is begun under the action. Examples are letter contracts, orders under basic ordering agreements, and provisioned item orders, for which the price has not been agreed upon before performance has begun. For policy relating to definitization of change orders, see 243.204-70 .

DFARS Parts

DFARS Appendix