Subpart 211.5 - LIQUIDATED DAMAGES
211.500 Scope.
This subpart and FAR subpart 11.5 do not apply to liquidated damages for comprehensive subcontracting plans under the Test Program for Negotiation of Comprehensive Small Business Subcontracting Plans. See 219.702-70 for coverage of liquidated damages for comprehensive subcontracting plans.
211.503 Contract clauses.
(b) Use the clause at FAR 52.211-12, Liquidated Damages—Construction, in all construction contracts exceeding $900,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work. Use of the clause in contracts of $900,000 or less is optional.
An official website of the United States Government
