Skip to main content
DFARSPGI

DFARSPGI

Change Number: DFARS PGI Change 02/15/2024
Effective Date: 02/15/2024

PGI 213.302-3 Obtaining contractor acceptance and modifying purchase orders.

PGI 213.302-3 Obtaining contractor acceptance and modifying purchase orders.

Generally, use unilateral modifications (see FAR 43.103) for—

(1) No-cost amended shipping instructions if—

(i) The amended shipping instructions modify a unilateral purchase order; and

(ii) The contractor agrees orally or in writing; and

(2) Any change made before work begins if—

(i) The change is within the scope of the original order;

(ii) The contractor agrees;

(iii) The modification references the contractor’s oral or written agreement; and

(iv) Block 13D of Standard Form 30, Amendment of Solicitation/Modification of Contract, is annotated to reflect the authority for issuance of the modification.