PART 5307
Acquisition Planning

[Revised 4 AUG 2004]

SUBPART 5307.1 — ACQUISITION PLANS

5307.102 Policy.
The acquisition team shall develop flexible acquisition strategies that provide rapid delivery of affordable capability to the warrior that meets their expectations. The priority established among cost, schedule and performance in accordance with 5311.002 shall drive the acquisition strategy.
5307.104 General procedures.

5307.104-90 Acquisition Strategy Panels (ASPs).
(a) General requirements.

(b) ASP chairpersons.

(c) ASP membership and content.

(d) ASP minutes. At the conclusion of the ASP, the program manager or contracting officer shall prepare ASP minutes and obtain approval of the ASP minutes from the ASP Chairperson.
5307.104-91 Air Force procedures for Single Acquisition Management Plans (SAMPs)/Commodity Acquisition Management Plans (CAMPs)/Integrated Program Summaries (IPSs).
(a) General requirements.

(b) Approval requirements.

(c) Content and review requirements. The SAMP/CAMP/IPS shall include all required elements of a written acquisition plan in accordance with FAR 7.105, as supplemented. The SAMP/CAMP/IPS approval authority determines the required content and coordination of the SAMP/CAMP/IPS, subject to law and higher regulation(s) (see FAR 7.1 as supplemented).
5307.104-92 Air Force procedures for Acquisition Plans (APs).
(a) For space related ACAT II programs and all ACAT III programs, if an acquisition plan is prepared in lieu of a SAMP/IPS, the PEO is the acquisition plan approval authority.
(b) For acquisitions within the AFPEO/CM portfolio, see 5337.503-90:
(1) For acquisitions > $500M, except for information technology services acquisitions that will be approved by ASD(NII), USD(AT&L) has delegated acquisition plan approval authority to ASAF(A).
(2) For acquisitions between $100M and $500M, ASAF(A) has delegated acquisition plan approval authority to AFPEO/CM.
(c) MAJCOMs and DRUs shall establish streamlined procedures for approval of “Other Contracting” acquisition plans.
(d) For commodity council acquisitions, the CSO is the acquisition plan approval authority.
5307.104-93 Air Force Procedures for Commodity Councils.
(a) The commodity council director shall prepare a commodity council charter which shall at a minimum:

(b) SAF/AQC shall review and approve all commodity council charters.
5307.105 Contents of Written Acquisition Plans
Acquisition plans must address whether foreign contractors can be permitted to participate at the prime contractor level in any or all contracts involved in the acquisition.