Previous PageTable Of ContentsNext Page

DLAD PART 42 – CONTRACT ADMINISTRATION



PART 42 – CONTRACT ADMINISTRATION

(Revised June 15 through PROCLTR 2015-09)

TABLE OF CONTENTS

SUBPART 42.3 – CONTRACT ADMINISTRATION OFFICE FUNCTIONS

42.302 Contract administration functions.

SUBPART 42.5 – POSTAWARD ORIENTATION

42.501 General.

SUBPART 42.11 – PRODUCTION SURVEILLANCE AND REPORTING

42.1103-90 Policy.

42.1107 Contract clause.

42.1190 Contract acceleration/status requests.

SUBPART 42.2 – RESERVED.

SUBPART 42.3 – CONTRACT ADMINISTRATION OFFICE FUNCTIONS

(Revised October 10 through PROCLTR 2014-77)

42.302 Contract administration functions. Contract Management Plans (CMPs) (see 7.105(b)(19)(S-90) are required for all Tailored Logistics Support Contracts (17.95) and long-term contracts (LTCs) that contain provisions for repricing during the contract term (16.190). Administration of these contracts must be in accordance with the CMP.

(a)(13)(B)(2) Contracting officers shall designate the payment office as DoD Activity Address Code (DoDAAC) SL4701 for Enterprise Business System (EBS) contracts, with the following exceptions:

(i) Use DoDAAC HQ0337 when DCMA will perform contract administration in Canada in accordance with DFARS PGI 225.870 (See the Federal Directory of Contract Administration Services (Fed DCAS) at https://pubapp.dcma.mil/CASD/browse_CasdPaymentOfficeReport.do?jboEvent=Search).

(ii) Use the payment code for the cognizant Defense Finance and Accounting System (DFAS) payment office as specified in the Federal Directory of Contract Administration Services Components (https://pubapp.dcma.mil/CASD/main.jsp) for all contracts with contract financing (e.g., progress payments, performance based payments, etc.).

(iii) Use DODAAC HQ0104 for contracts with multiple Lines of Accounting (a mix of DLA and from the military services or other non-DLA activities, such as the Army, Navy, Air Force, Marines, Air National Guard, FEMA, NASA, and DHS.

SUBPART 42.5 – POSTAWARD ORIENTATION

42.501(e)(S-90) Post award orientation agendas. Post award orientation agendas should include discussion of dispute avoidance, early dispute resolution, and alternative dispute resolution.

SUBPART 42.11 – PRODUCTION SURVEILLANCE AND REPORTING

(Revised November 7, 2013 through PROCLTR 2014-20)

42.1103-90 Policy. For all contracts, the post-award acquisition specialist is responsible for the actions shown below:

(a) Performing analysis and resolving post-award requests from the supply planner or customer account specialist (CAS), to ensure correct products are delivered and to achieve current timeline, accuracy, customer satisfaction and administrative and production lead time (ALT/PLT) targets;

(b) Negotiating settlements for contractual changes that are beneficial to the Government in terms of costs and conditions within current timeline targets;

(c) Monitoring vendor performance to ensure compliance with terms and taking action for non-compliance; and

(d) Applying DLA business practices, in coordination with the supply planner or customer account specialist, in contract termination decisions for convenience or default if requirements change or vendors fail to perform.

42.1107 Contract clauses. Use 52.242-9005 in solicitations and contracts for perishable medical items being shipped by commercial carrier except those to air and water terminals for movement via the Defense Transportation System.

42.1190 Contract acceleration/status requests. When it is determined that a customer’s need date may require a shorter delivery, the supply planner or the customer account specialist will follow the policies and processes for expediting delivery in Cross-Process Policy Memorandum CP-12-001, Sales Order Expedite and Customer Inquiry Policy, dated December 11, 2012 (available on eWorkplace, Logistics Operations (J3), Shared Documents, J3 Policies and Procedures, Cross Process).

SUBPART 42.13 – RESERVED.

SUBPART 42.14 – TRAFFIC AND TRANSPORATION MANAGEMENT

(Revised June 15, 2015 through PROCLTR 2015-09)

42.14(90) Use the clause at 52.242-9001 in solicitations and contracts for Federal Supply Group (FSG) 34, industrial plant equipment (IPE), whether for new procurements or rebuild/remanufacture/retrofit.

42.14(91) Reserved.

42.14-92 Notice of availability. Use clause 52.242-9012 in clothing and textiles, medical and subsistence acquisitions with shipments to the Federal Republic of Germany for foreign military sales where a notice of availability is required. The contract specialist shall fill-in needed text.

SUBPART 42.72 – RESERVED.

SUBPART 42.74 – RESERVED.

Previous PageTop Of PageTable Of ContentsNext Page