552.236-76 Basis of Award— Sealed Bidding Construction.
As prescribed in 536.270-5 (c), insert a provision substantially the same as the following provision:
Basis of Award - Sealed Bidding Construction (Mar 2019)
A bid may be rejected as nonresponsive if the bid is materially unbalanced as to bid prices. A bid is unbalanced when the bid is based on prices significantly less than cost for some work and significantly overstated for other work.
(End of provision)
Alternate I (Mar 2019). As prescribed in 536.270-5 (c), redesignate the basic provision as paragraph (a) and add the following paragraph (b) to the basic provision:
(b)(1) The low bidder for purposes of award is the responsible bidder offering the lowest aggregate price for:
(i) The base requirement; plus
(ii) All options designated to be evaluated.